Briefing on Taylor County Paul Storage

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
205 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2028-06-30
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Taylor County Paul Storage is a 205 MW Battery project in Texas, currently active.

DM-TCP, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-06-30.

Queue ID
ERCOT-26INR0618
Location
Taylor, Texas
Technology
Battery
Developer
DM-TCP, LLC
Market / region
ERCOT
Point of interconnection
6260 Abilene South Substation 138kV

What stands out

1

Taylor County Paul Storage is a 205 MW Battery project in Texas with status active.

2

DM-TCP, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2028-06-30.

Market and operating context

Queue date
2024-12-19
Proposed COD
2028-06-30
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Taylor County Paul Storage — verified asset snapshot

FieldValue
Queue IDERCOT-26INR0618
LocationTaylor, Texas
TechnologyBattery
DeveloperDM-TCP, LLC
Market / regionERCOT
Point of interconnection6260 Abilene South Substation 138kV
Queue date2024-12-19
Proposed COD2028-06-30