Briefing on Tapaderos Solar

Entity Briefing
Generated Oct 20, 2026·Dataset freshness not reported
302 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
ERCOT
Market / region
2028-09-19
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Tapaderos Solar is a 302 MW Solar+Battery project in Texas, currently active.

Tapaderos Solar, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-09-19.

Queue ID
ERCOT-28INR0194
Location
Young, Texas
Technology
Solar+Battery
Developer
Tapaderos Solar, LLC
Market / region
ERCOT
Point of interconnection
TAP 345kV #1435 Long Creek - #1430 Graham SES

What stands out

1

Tapaderos Solar is a 302 MW Solar+Battery project in Texas with status active.

2

Tapaderos Solar, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2028-09-19.

4

Latest linked story: “Solar reinvestment zone public hearing upcoming” (The Graham Leader, 2026-01-02).

Market and operating context

Queue date
2024-11-19
Proposed COD
2028-09-19
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Tapaderos Solar — verified asset snapshot

FieldValue
Queue IDERCOT-28INR0194
LocationYoung, Texas
TechnologySolar+Battery
DeveloperTapaderos Solar, LLC
Market / regionERCOT
Point of interconnectionTAP 345kV #1435 Long Creek - #1430 Graham SES
Queue date2024-11-19
Proposed COD2028-09-19