Briefing/projectactive
Tall Saddle Solar is a 252 MW Solar project in Texas, currently active.
Tall Saddle Solar, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2029-10-15.
- Queue ID
- ERCOT-27INR0309
- Location
- Kenedy, Texas
- Technology
- Solar
- Developer
- Tall Saddle Solar, LLC
- Market / region
- ERCOT
- Point of interconnection
- 80076 AJO SUBSTATION 345kV
What stands out
1
Tall Saddle Solar is a 252 MW Solar project in Texas with status active.
2
Tall Saddle Solar, LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2029-10-15.
Market and operating context
- Queue date
- 2024-07-01
- Proposed COD
- 2029-10-15
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.