Briefing/projectactive
Surplus; J1369 is a 50 MW Battery project in Indiana, currently active.
The reported queue phase is IA Executed. Proposed COD is 2022-07-01.
- Queue ID
- MISO-S1026
- Location
- Dubois, Indiana
- Technology
- Battery
- Market / region
- MISO
- Point of interconnection
- Dubois - Culley 138kV line
What stands out
1
Surplus; J1369 is a 50 MW Battery project in Indiana with status active.
2
The reported queue phase is IA Executed; proposed COD is 2022-07-01.
Market and operating context
- Queue date
- 2022-05-26
- Proposed COD
- 2022-07-01
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.