Briefing/projectactive
SUNRISE POWER IMPROVEMENT is a 656 MW Gas project in California, currently active.
The reported queue phase is C13. Proposed COD is 2024-05-11.
- Queue ID
- CAISO-1745
- Location
- Kern, California
- Technology
- Gas
- Market / region
- CAISO
- Point of interconnection
- Midway 230 kV
What stands out
1
SUNRISE POWER IMPROVEMENT is a 656 MW Gas project in California with status active.
2
The reported queue phase is C13; proposed COD is 2024-05-11.
3
Latest linked story: “HULL STREET ENERGY AGREES TO ACQUIRE CALIFORNIA NATURAL GAS-FIRED PLANT” (PR Newswire, 2023-04-20).
Market and operating context
- Queue date
- 2020-04-15
- Proposed COD
- 2024-05-11
- IA status
- System Impact Study
- Study phase
- C13
- Service type
- ERIS
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.