Sullivan BESS is a 72 MW Solar+Battery project in Texas, currently active.
Sullivan Solar LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2029-02-25.
- Queue ID
- ERCOT-26INR0444
- Location
- Hidalgo, Texas
- Technology
- Solar+Battery
- Developer
- Sullivan Solar LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap 138kV 8798 La Grulla - 8355 Goodwin
What stands out
1
Sullivan BESS is a 72 MW Solar+Battery project in Texas with status active.
2
Sullivan Solar LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2029-02-25.
Market and operating context
- Queue date
- 2024-03-22
- Proposed COD
- 2029-02-25
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.