Briefing/projectactive
Strawberry Dunes Solar SLF is a 101 MW Solar+Battery project in Texas, currently active.
Strawberry Dunes LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-06-30.
- Queue ID
- ERCOT-28INR0208
- Location
- Atascosa, Texas
- Technology
- Solar+Battery
- Developer
- Strawberry Dunes LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap 138kV ROSSVILLESB8 (5718) to OAKSSW8 (5713)
What stands out
1
Strawberry Dunes Solar SLF is a 101 MW Solar+Battery project in Texas with status active.
2
Strawberry Dunes LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2028-06-30.
Market and operating context
- Queue date
- 2025-02-14
- Proposed COD
- 2028-06-30
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.