Briefing/projectactive
Stinger Energy Storage is a 201 MW Battery project in Texas, currently active.
Stinger Energy Storage LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-03-01.
- Queue ID
- ERCOT-26INR0343
- Location
- Harris, Texas
- Technology
- Battery
- Developer
- Stinger Energy Storage LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap Atascocita 138kV Substation (Bus # 40130) - Lake Houston (Bus #40820)
What stands out
1
Stinger Energy Storage is a 201 MW Battery project in Texas with status active.
2
Stinger Energy Storage LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2028-03-01.
Market and operating context
- Queue date
- 2023-11-14
- Proposed COD
- 2028-03-01
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.