Briefing on Stephens Ranch Wind Repower

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
12 MW
Proposed capacity
active
Current status
Wind
Technology
ERCOT
Market / region
2027-10-01
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Stephens Ranch Wind Repower is a 12 MW Wind project in Texas, currently active.

Stephens Ranch Wind Energy, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-10-01.

Queue ID
ERCOT-25INR0439
Location
Borden, Texas
Technology
Wind
Developer
Stephens Ranch Wind Energy, LLC
Market / region
ERCOT
Point of interconnection
59900 Long Draw 345 kV

What stands out

1

Stephens Ranch Wind Repower is a 12 MW Wind project in Texas with status active.

2

Stephens Ranch Wind Energy, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2027-10-01.

Market and operating context

Queue date
2023-06-28
Proposed COD
2027-10-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Stephens Ranch Wind Repower — verified asset snapshot

FieldValue
Queue IDERCOT-25INR0439
LocationBorden, Texas
TechnologyWind
DeveloperStephens Ranch Wind Energy, LLC
Market / regionERCOT
Point of interconnection59900 Long Draw 345 kV
Queue date2023-06-28
Proposed COD2027-10-01