Briefing on Stella 2 Wind

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
201 MW
Proposed capacity
suspended
Current status
Wind
Technology
ERCOT
Market / region
2022-12-15
Proposed COD
Facility Study
Queue phase
Briefing/projectsuspended

Stella 2 Wind is a 201 MW Wind project in Texas, currently suspended.

Eon is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2022-12-15.

Queue ID
ERCOT-16INR0012
Location
Kenedy, Texas
Technology
Wind
Developer
Eon
Market / region
ERCOT
Point of interconnection
tap 345kV 80076 Ajo - 80071 Zorillo

What stands out

1

Stella 2 Wind is a 201 MW Wind project in Texas with status suspended.

2

Eon is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2022-12-15.

4

Latest linked story: “E.ON celebrates new wind farm in Kenedy County” (Corpus Christi Caller-Times, 2019-08-09).

Market and operating context

Queue date
2013-06-12
Proposed COD
2022-12-15
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Stella 2 Wind — verified asset snapshot

FieldValue
Queue IDERCOT-16INR0012
LocationKenedy, Texas
TechnologyWind
DeveloperEon
Market / regionERCOT
Point of interconnectiontap 345kV 80076 Ajo - 80071 Zorillo
Queue date2013-06-12
Proposed COD2022-12-15