Query
Stegall Solar
Type
Entity Briefing
Entity
Stegall Solar
Generated
2026-10-19T15:02:06.767Z

Briefing on Stegall Solar

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
82 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
ERCOT
Market / region
2027-05-30
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Stegall Solar is a 82 MW Solar+Battery project in Texas, currently active.

BT Martin Solar, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-05-30.

Queue ID
ERCOT-25INR0497
Location
Robertson, Texas
Technology
Solar+Battery
Developer
BT Martin Solar, LLC
Market / region
ERCOT
Point of interconnection
Elliott (Bus #53) to Franklin (Bus #57) 69kV Transmission Line

What stands out

1

Stegall Solar is a 82 MW Solar+Battery project in Texas with status active.

2

BT Martin Solar, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2027-05-30.

Market and operating context

Queue date
2023-08-21
Proposed COD
2027-05-30
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Stegall Solar — verified asset snapshot

FieldValue
Queue IDERCOT-25INR0497
LocationRobertson, Texas
TechnologySolar+Battery
DeveloperBT Martin Solar, LLC
Market / regionERCOT
Point of interconnectionElliott (Bus #53) to Franklin (Bus #57) 69kV Transmission Line
Queue date2023-08-21
Proposed COD2027-05-30