Starling Storage is a 64 MW Solar+Battery project in Texas, currently active.
Starling Storage, LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2027-05-15.
- Queue ID
- ERCOT-23INR0181
- Location
- Gonzales, Texas
- Technology
- Solar+Battery
- Developer
- Starling Storage, LLC
- Market / region
- ERCOT
- Point of interconnection
- tap 138kV 7224 Luling - 7245 Gonzales
What stands out
Starling Storage is a 64 MW Solar+Battery project in Texas with status active.
Starling Storage, LLC is the reported developer.
The reported queue phase is IA Executed; proposed COD is 2027-05-15.
Latest linked story: “Duke Energy to invest $500 million in battery storage in the Carolinas over the next 15 years” (Duke Energy | News Center, 2018-10-10).
Market and operating context
- Queue date
- 2021-01-25
- Proposed COD
- 2027-05-15
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.