Briefing on SR Rochelle II Solar

Entity Briefing
Generated Oct 17, 2026·Dataset freshness not reported
90 MW
Proposed capacity
active
Current status
Solar
Technology
Southeast
Market / region
2026-11-01
Proposed COD
Construction
Queue phase
Briefing/projectactive

SR Rochelle II Solar is a 90 MW Solar project in Georgia, currently active.

The reported queue phase is Construction. Proposed COD is 2026-11-01.

Queue ID
GTC-GI-183
Location
Wilcox, Georgia
Technology
Solar
Market / region
Southeast
Point of interconnection
Fitzgerald - Pitts 115 kV TL

What stands out

1

SR Rochelle II Solar is a 90 MW Solar project in Georgia with status active.

2

The reported queue phase is Construction; proposed COD is 2026-11-01.

Market and operating context

Queue date
2023-09-20
Proposed COD
2026-11-01
IA status
Construction
Study phase
Construction

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

SR Rochelle II Solar — verified asset snapshot

FieldValue
Queue IDGTC-GI-183
LocationWilcox, Georgia
TechnologySolar
Market / regionSoutheast
Point of interconnectionFitzgerald - Pitts 115 kV TL
Queue date2023-09-20
Proposed COD2026-11-01
IA statusConstruction