Query
SR Dry Branch queue pipeline — 1 projects by technology and status
Type
Entity Briefing
Entity
Baker Branch Solar
ISO/RTO
isone
Generated
2026-10-10T16:49:36.530Z

Briefing on Baker Branch Solar

Entity Briefing
Generated Oct 10, 2026·Dataset freshness not reported
469 MW
Proposed capacity
active
Current status
Solar
Technology
ERCOT
Market / region
2026-05-31
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

Baker Branch Solar is a 469 MW Solar project in Texas, currently active.

Ørsted is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2026-05-31.

Queue ID
ERCOT-23INR0026
Location
Lamar, Texas
Technology
Solar
Developer
Ørsted
Market / region
ERCOT
Point of interconnection
tap 345kV 1692 Paris - 1690 Valley

What stands out

1

Baker Branch Solar is a 469 MW Solar project in Texas with status active.

2

Ørsted is the reported developer.

3

The reported queue phase is IA Executed; proposed COD is 2026-05-31.

4

Latest linked story: “Ørsted's solar, battery portfolio sale indicates growing generating asset values” (S&P Global, 2025-02-05).

Market and operating context

Queue date
2020-03-26
Proposed COD
2026-05-31
IA status
IA Executed
Study phase
IA Executed

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Baker Branch Solar — verified asset snapshot

FieldValue
Queue IDERCOT-23INR0026
LocationLamar, Texas
TechnologySolar
DeveloperØrsted
Market / regionERCOT
Point of interconnectiontap 345kV 1692 Paris - 1690 Valley
Queue date2020-03-26
Proposed COD2026-05-31