Query
SR Dry Branch
Type
Entity Briefing
Entity
SR Dry Branch
Generated
2026-10-06T22:41:18.036Z

Briefing on SR Dry Branch

Entity Briefing
Generated Oct 6, 2026·Dataset freshness not reported
172 MW
Proposed capacity
active
Current status
Solar
Technology
Southeast
Market / region
2029-12-31
Proposed COD
System Impact Study
Queue phase
Briefing/projectactive

SR Dry Branch is a 172 MW Solar project in Georgia, currently active.

The reported queue phase is System Impact Study. Proposed COD is 2029-12-31.

Queue ID
GTC-GI-208
Location
Twiggs, Georgia
Technology
Solar
Market / region
Southeast
Point of interconnection
Bonaire Primary - South Macon 230 kV Line

What stands out

1

SR Dry Branch is a 172 MW Solar project in Georgia with status active.

2

The reported queue phase is System Impact Study; proposed COD is 2029-12-31.

Market and operating context

Queue date
2025-01-09
Proposed COD
2029-12-31
IA status
System Impact Study
Study phase
System Impact Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

SR Dry Branch — verified asset snapshot

FieldValue
Queue IDGTC-GI-208
LocationTwiggs, Georgia
TechnologySolar
Market / regionSoutheast
Point of interconnectionBonaire Primary - South Macon 230 kV Line
Queue date2025-01-09
Proposed COD2029-12-31
IA statusSystem Impact Study