Query
SOLEIL CANTIL
Type
Entity Briefing
Entity
SOLEIL CANTIL
Generated
2026-10-11T22:30:34.898Z

Briefing on SOLEIL CANTIL

Entity Briefing
Generated Oct 11, 2026·Dataset freshness not reported
597 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
CAISO
Market / region
2033-02-26
Proposed COD
C14
Queue phase
Briefing/projectactive

SOLEIL CANTIL is a 597 MW Solar+Battery project in California, currently active.

The reported queue phase is C14. Proposed COD is 2033-02-26.

Queue ID
CAISO-2078
Location
Kern, California
Technology
Solar+Battery
Market / region
CAISO
Point of interconnection
Windhub Substation 500kV

What stands out

1

SOLEIL CANTIL is a 597 MW Solar+Battery project in California with status active.

2

The reported queue phase is C14; proposed COD is 2033-02-26.

Market and operating context

Queue date
2021-04-15
Proposed COD
2033-02-26
IA status
System Impact Study
Study phase
C14
Service type
NRIS

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

SOLEIL CANTIL — verified asset snapshot

FieldValue
Queue IDCAISO-2078
LocationKern, California
TechnologySolar+Battery
Market / regionCAISO
Point of interconnectionWindhub Substation 500kV
Queue date2021-04-15
Proposed COD2033-02-26
IA statusSystem Impact Study