Query
Snap Jaw BESS
Type
Entity Briefing
Entity
Snap Jaw BESS
State
TN
Technology
battery
Generated
2026-10-19T06:53:09.212Z

Briefing on Snap Jaw BESS

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
201 MW
Proposed capacity
suspended
Current status
Other
Technology
ERCOT
Market / region
2028-06-01
Proposed COD
Facility Study
Queue phase
Briefing/projectsuspended

Snap Jaw BESS is a 201 MW Other project in Texas, currently suspended.

Moccasin Pointe Grid, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-06-01.

Queue ID
ERCOT-23INR0217
Location
Harris, Texas
Technology
Other
Developer
Moccasin Pointe Grid, LLC
Market / region
ERCOT
Point of interconnection
tap 138kV 40941 La Porte - 40200 Bimont (Air Liquide)

What stands out

1

Snap Jaw BESS is a 201 MW Other project in Texas with status suspended.

2

Moccasin Pointe Grid, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2028-06-01.

Market and operating context

Queue date
2021-04-04
Proposed COD
2028-06-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Snap Jaw BESS — verified asset snapshot

FieldValue
Queue IDERCOT-23INR0217
LocationHarris, Texas
TechnologyOther
DeveloperMoccasin Pointe Grid, LLC
Market / regionERCOT
Point of interconnectiontap 138kV 40941 La Porte - 40200 Bimont (Air Liquide)
Queue date2021-04-04
Proposed COD2028-06-01