Briefing/projectactive
Silver Hills Windpower is a 54 MW Wind project in Texas, currently active.
Silver Hills Windpower, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2029-06-01.
- Queue ID
- ERCOT-27INR0512
- Location
- Howard, Texas
- Technology
- Wind
- Developer
- Silver Hills Windpower, LLC
- Market / region
- ERCOT
- Point of interconnection
- 10066 Prong Moss Switch 138kV
What stands out
1
Silver Hills Windpower is a 54 MW Wind project in Texas with status active.
2
Silver Hills Windpower, LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2029-06-01.
Market and operating context
- Queue date
- 2025-04-21
- Proposed COD
- 2029-06-01
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.