Query
Sherbino II BESS SLF
Type
Entity Briefing
Entity
Sherbino II BESS SLF
State
TN
Technology
battery
Generated
2026-10-20T02:58:56.391Z

Briefing on Sherbino II BESS SLF

Entity Briefing
Generated Oct 20, 2026·Dataset freshness not reported
77 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2027-04-19
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

Sherbino II BESS SLF is a 77 MW Battery project in Texas, currently active.

Phoenix Battery Storage, LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2027-04-19.

Queue ID
ERCOT-26INR0296
Location
Pecos, Texas
Technology
Battery
Developer
Phoenix Battery Storage, LLC
Market / region
ERCOT
Point of interconnection
38430 TNMP White baker Switching Station 138kV

What stands out

1

Sherbino II BESS SLF is a 77 MW Battery project in Texas with status active.

2

Phoenix Battery Storage, LLC is the reported developer.

3

The reported queue phase is IA Executed; proposed COD is 2027-04-19.

Market and operating context

Queue date
2023-11-30
Proposed COD
2027-04-19
IA status
IA Executed
Study phase
IA Executed

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Sherbino II BESS SLF — verified asset snapshot

FieldValue
Queue IDERCOT-26INR0296
LocationPecos, Texas
TechnologyBattery
DeveloperPhoenix Battery Storage, LLC
Market / regionERCOT
Point of interconnection38430 TNMP White baker Switching Station 138kV
Queue date2023-11-30
Proposed COD2027-04-19