Briefing on SCOTT CROSSING SOLAR SLF

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
364 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
ERCOT
Market / region
2027-09-01
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

SCOTT CROSSING SOLAR SLF is a 364 MW Solar+Battery project in Texas, currently active.

FRESH AIR ENERGY II, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-09-01.

Queue ID
ERCOT-27INR0020
Location
Haskell, Texas
Technology
Solar+Battery
Developer
FRESH AIR ENERGY II, LLC
Market / region
ERCOT
Point of interconnection
Tap 345kV 60514 Clear Crossing - 60507

What stands out

1

SCOTT CROSSING SOLAR SLF is a 364 MW Solar+Battery project in Texas with status active.

2

FRESH AIR ENERGY II, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2027-09-01.

Market and operating context

Queue date
2023-03-27
Proposed COD
2027-09-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

SCOTT CROSSING SOLAR SLF — verified asset snapshot

FieldValue
Queue IDERCOT-27INR0020
LocationHaskell, Texas
TechnologySolar+Battery
DeveloperFRESH AIR ENERGY II, LLC
Market / regionERCOT
Point of interconnectionTap 345kV 60514 Clear Crossing - 60507
Queue date2023-03-27
Proposed COD2027-09-01