50 MW
Proposed capacity
active
Current status
Solar
Technology
PJM
Market / region
2027-10-01
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

Scioty Solar is a 50 MW Solar project in Ohio, currently active.

The reported queue phase is IA Executed. Proposed COD is 2027-10-01.

Queue ID
PJM-AG1-554
Location
Hardin, Ohio
Technology
Solar
Market / region
PJM
Point of interconnection
South Kenton 138 kV

What stands out

1

Scioty Solar is a 50 MW Solar project in Ohio with status active.

2

The reported queue phase is IA Executed; proposed COD is 2027-10-01.

Market and operating context

Queue date
2020-09-30
Proposed COD
2027-10-01
IA status
IA Executed
Study phase
IA Executed
Service type
NRIS

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Scioty Solar — verified asset snapshot

FieldValue
Queue IDPJM-AG1-554
LocationHardin, Ohio
TechnologySolar
Market / regionPJM
Point of interconnectionSouth Kenton 138 kV
Queue date2020-09-30
Proposed COD2027-10-01
IA statusIA Executed