Briefing/projectactive
SCHNEIDER GAS RICE is a 113 MW Gas project in Texas, currently active.
LCRA is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2030-12-17.
- Queue ID
- ERCOT-29INR0176
- Location
- Caldwell, Texas
- Technology
- Gas
- Developer
- LCRA
- Market / region
- ERCOT
- Point of interconnection
- Double Tap 345kV #7042 Zorn - #7040 Austrop and #7042 Zorn - #9074 Lytton Springs
What stands out
1
SCHNEIDER GAS RICE is a 113 MW Gas project in Texas with status active.
2
LCRA is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2030-12-17.
4
Latest linked story: “U.S. colleges talk green. But they have a dirty secret” (Reuters, 2022-11-11).
Market and operating context
- Queue date
- 2025-07-29
- Proposed COD
- 2030-12-17
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.