Sayle Storage SLF is a 122 MW Solar+Battery project in Texas, currently active.
Sayle Storage LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-05-31.
- Queue ID
- ERCOT-27INR0260
- Location
- Jackson, Texas
- Technology
- Solar+Battery
- Developer
- Sayle Storage LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap 69kV #5522 Edna - #5518 El Toro SW
What stands out
Sayle Storage SLF is a 122 MW Solar+Battery project in Texas with status active.
Sayle Storage LLC is the reported developer.
The reported queue phase is Facility Study; proposed COD is 2027-05-31.
Latest linked story: “US DOE closes US$26.5 billion loan package to utility Southern Company for 16GW of capacity, including BESS” (Energy-Storage.News, 2026-03-09).
Market and operating context
- Queue date
- 2024-06-03
- Proposed COD
- 2027-05-31
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.