Briefing/projectactive
Sagebrush Wind is a 200 MW Wind project in Texas, currently active.
ACE DevCo NC, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2029-12-01.
- Queue ID
- ERCOT-28INR0386
- Location
- Nolan, Texas
- Technology
- Wind
- Developer
- ACE DevCo NC, LLC
- Market / region
- ERCOT
- Point of interconnection
- TAP 345KV 11420 SWEETWATER EAST - 11406 CENTRAL BLUFF
What stands out
1
Sagebrush Wind is a 200 MW Wind project in Texas with status active.
2
ACE DevCo NC, LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2029-12-01.
Market and operating context
- Queue date
- 2025-07-29
- Proposed COD
- 2029-12-01
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.