Briefing/projectactive
Roxton Solar is a 117 MW Solar+Battery project in Texas, currently active.
Roxton Solar, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-02-18.
- Queue ID
- ERCOT-26INR0470
- Location
- Lamar, Texas
- Technology
- Solar+Battery
- Developer
- Roxton Solar, LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap 138 KV Bois Pump (1835) - Brookston (1833)
What stands out
1
Roxton Solar is a 117 MW Solar+Battery project in Texas with status active.
2
Roxton Solar, LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2028-02-18.
4
Latest linked story: “SB Energy and Mitsui unit sign PPA for 418MWp Texas project” (PV Tech, 2021-08-30).
Market and operating context
- Queue date
- 2024-11-26
- Proposed COD
- 2028-02-18
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.