Roost Energy Storage is a 102 MW Battery project in Texas, currently active.
Bluff Creek Energy Storage LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-04-19.
- Queue ID
- ERCOT-24INR0519
- Location
- Scurry, Texas
- Technology
- Battery
- Developer
- Bluff Creek Energy Storage LLC
- Market / region
- ERCOT
- Point of interconnection
- KNDRSACRC Bus #11130 to Knapp Substation Bus #1310
What stands out
1
Roost Energy Storage is a 102 MW Battery project in Texas with status active.
2
Bluff Creek Energy Storage LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2028-04-19.
Market and operating context
- Queue date
- 2023-01-30
- Proposed COD
- 2028-04-19
- IA status
- Facility Study
- Study phase
- Facility Study