Briefing/projectactive
Roboman Solar is a 273 MW Solar project in Texas, currently active.
Roboman Solar, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2029-07-01.
- Queue ID
- ERCOT-27INR0453
- Location
- Coke, Texas
- Technology
- Solar
- Developer
- Roboman Solar, LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap 345 kV (#76009) Twin Buttes – (#76090) Divide Ckt 1
What stands out
1
Roboman Solar is a 273 MW Solar project in Texas with status active.
2
Roboman Solar, LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2029-07-01.
Market and operating context
- Queue date
- 2025-07-07
- Proposed COD
- 2029-07-01
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.