Rhapsody Storage is a 206 MW Battery project in Texas, currently active.
Destiny Storage, LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2026-05-20.
- Queue ID
- ERCOT-24INR0397
- Location
- Harris, Texas
- Technology
- Battery
- Developer
- Destiny Storage, LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap 138kV 40390 Crosby - 40680 Placid Ckt 86
What stands out
Rhapsody Storage is a 206 MW Battery project in Texas with status active.
Destiny Storage, LLC is the reported developer.
The reported queue phase is IA Executed; proposed COD is 2026-05-20.
Latest linked story: “Cypress Creek Renewables secures US$133 million for 200MW Texas BESS” (Energy-Storage.News, 2025-03-13).
Market and operating context
- Queue date
- 2022-08-16
- Proposed COD
- 2026-05-20
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.