Briefing on Razorbill Solar

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
240 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
ERCOT
Market / region
2027-12-15
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Razorbill Solar is a 240 MW Solar+Battery project in Texas, currently active.

RWE Solar Development, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-12-15.

Queue ID
ERCOT-22INR0244
Location
Matagorda, Texas
Technology
Solar+Battery
Developer
RWE Solar Development, LLC
Market / region
ERCOT
Point of interconnection
tap 345kV 5915 STP to 44200 Hillje 345kV Ckt 64

What stands out

1

Razorbill Solar is a 240 MW Solar+Battery project in Texas with status active.

2

RWE Solar Development, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2027-12-15.

Market and operating context

Queue date
2020-01-02
Proposed COD
2027-12-15
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Razorbill Solar — verified asset snapshot

FieldValue
Queue IDERCOT-22INR0244
LocationMatagorda, Texas
TechnologySolar+Battery
DeveloperRWE Solar Development, LLC
Market / regionERCOT
Point of interconnectiontap 345kV 5915 STP to 44200 Hillje 345kV Ckt 64
Queue date2020-01-02
Proposed COD2027-12-15