Hecate Energy Arkansas Wind is a 1 GW Wind project in Texas, currently active.
Hecate Energy Gulf Wind LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2030-06-01.
- Queue ID
- ERCOT-30INR0004
- Location
- San Patricio, Texas
- Technology
- Wind
- Developer
- Hecate Energy Gulf Wind LLC
- Market / region
- ERCOT
- Point of interconnection
- 8659 Naismith 345kV
What stands out
Hecate Energy Arkansas Wind is a 1 GW Wind project in Texas with status active.
Hecate Energy Gulf Wind LLC is the reported developer.
The reported queue phase is Facility Study; proposed COD is 2030-06-01.
Latest linked story: “Bechtel wins $453M Michigan solar project” (Construction Dive, 2024-09-16).
Market and operating context
- Queue date
- 2023-06-28
- Proposed COD
- 2030-06-01
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.