Prairie Branch BESS is a 310 MW Solar+Battery project in Texas, currently active.
Prairie Branch Energy, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2029-12-01.
- Queue ID
- ERCOT-28INR0423
- Location
- Montague, Texas
- Technology
- Solar+Battery
- Developer
- Prairie Branch Energy, LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap 345kV #1730 Krum West - #6111 Riley Ckt 1
What stands out
1
Prairie Branch BESS is a 310 MW Solar+Battery project in Texas with status active.
2
Prairie Branch Energy, LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2029-12-01.
Market and operating context
- Queue date
- 2025-09-09
- Proposed COD
- 2029-12-01
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.