Query
Point Marion L&D Hydroelectric Project
Type
Entity Briefing
Entity
Point Marion L&D Hydroelectric Project
Technology
hydro
Generated
2026-10-17T20:05:19.318Z

Briefing on Point Marion L&D Hydroelectric Project

Entity Briefing
Generated Oct 17, 2026·Dataset freshness not reported
5 MW
Capacity
Planned
Current status
2
Generators
Briefing/plantPlanned

Point Marion L&D Hydroelectric Project is a 5 MW Conventional Hydroelectric asset in PJM Interconnection, currently Planned.

Point Marion L&D Hydroelectric Project is reported in Pennsylvania under Rye Development. Available operating and financial measures include $1415/kW reported CapEx.

Location
Fayette, Pennsylvania
Technology
Conventional Hydroelectric
Owner / parent
Rye Development
Operator
Rye Development
Grid
PJM Interconnection
Plant ID
62384

What stands out

1

Point Marion L&D Hydroelectric Project is a 5 MW Conventional Hydroelectric asset in Pennsylvania with status Planned.

2

Available financial measures include $1415/kW CapEx.

Market and operating context

ISO / market
PJM Interconnection
Balancing authority
PJM Interconnection, LLC
NERC region
RFC
State rank
#29 of 31
National rank
#863 of 1,462

Why it matters

For this asset in PJM Interconnection, operating status, generation, ownership, and linked events are the primary facts for performance and asset-level diligence. The exact chart and source-linked records below let the reader test those facts before moving to a deeper report.

Point Marion L&D Hydroelectric Project — verified asset snapshot

FieldValue
LocationFayette, Pennsylvania
TechnologyConventional Hydroelectric
Owner / parentRye Development
OperatorRye Development
GridPJM Interconnection
Plant ID62384
ISO / marketPJM Interconnection
Balancing authorityPJM Interconnection, LLC