Briefing on Pitts Dudik II

Entity Briefing
Generated Oct 18, 2026·Dataset freshness not reported
30 MW
Proposed capacity
active
Current status
Solar
Technology
ERCOT
Market / region
2026-04-24
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

Pitts Dudik II is a 30 MW Solar project in Texas, currently active.

Pitts Dudik II is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2026-04-24.

Queue ID
ERCOT-24INR0364
Location
Hill, Texas
Technology
Solar
Developer
Pitts Dudik II
Market / region
ERCOT
Point of interconnection
138 kV Ash Creek Switch (#3473)

What stands out

1

Pitts Dudik II is a 30 MW Solar project in Texas with status active.

2

Pitts Dudik II is the reported developer.

3

The reported queue phase is IA Executed; proposed COD is 2026-04-24.

Market and operating context

Queue date
2022-07-18
Proposed COD
2026-04-24
IA status
IA Executed
Study phase
IA Executed

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Pitts Dudik II — verified asset snapshot

FieldValue
Queue IDERCOT-24INR0364
LocationHill, Texas
TechnologySolar
DeveloperPitts Dudik II
Market / regionERCOT
Point of interconnection138 kV Ash Creek Switch (#3473)
Queue date2022-07-18
Proposed COD2026-04-24