Briefing/projectactive
Pitts Dudik II is a 30 MW Solar project in Texas, currently active.
Pitts Dudik II is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2026-04-24.
- Queue ID
- ERCOT-24INR0364
- Location
- Hill, Texas
- Technology
- Solar
- Developer
- Pitts Dudik II
- Market / region
- ERCOT
- Point of interconnection
- 138 kV Ash Creek Switch (#3473)
What stands out
1
Pitts Dudik II is a 30 MW Solar project in Texas with status active.
2
Pitts Dudik II is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2026-04-24.
Market and operating context
- Queue date
- 2022-07-18
- Proposed COD
- 2026-04-24
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.