Briefing on Pioneer Path Energy Storage 2

Entity Briefing
Generated Oct 20, 2026·Dataset freshness not reported
102 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2027-12-01
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Pioneer Path Energy Storage 2 is a 102 MW Battery project in Texas, currently active.

Tempus Power management LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-12-01.

Queue ID
ERCOT-27INR0423
Location
Robertson, Texas
Technology
Battery
Developer
Tempus Power management LLC
Market / region
ERCOT
Point of interconnection
Tap 345kV 39950 TNP ONE PLANT - 3400 TWIN OAK Ckt 2

What stands out

1

Pioneer Path Energy Storage 2 is a 102 MW Battery project in Texas with status active.

2

Tempus Power management LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2027-12-01.

Market and operating context

Queue date
2025-02-03
Proposed COD
2027-12-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Pioneer Path Energy Storage 2 — verified asset snapshot

FieldValue
Queue IDERCOT-27INR0423
LocationRobertson, Texas
TechnologyBattery
DeveloperTempus Power management LLC
Market / regionERCOT
Point of interconnectionTap 345kV 39950 TNP ONE PLANT - 3400 TWIN OAK Ckt 2
Queue date2025-02-03
Proposed COD2027-12-01