Briefing on Pinnington Solar

Entity Briefing
Generated Oct 20, 2026·Dataset freshness not reported
654 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
ERCOT
Market / region
2026-04-30
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

Pinnington Solar is a 654 MW Solar+Battery project in Texas, currently active.

Hecate Energy Longhorn Solar LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2026-04-30.

Queue ID
ERCOT-24INR0010
Location
Jack, Texas
Technology
Solar+Battery
Developer
Hecate Energy Longhorn Solar LLC
Market / region
ERCOT
Point of interconnection
1506 Long Hollow Switch 345kV

What stands out

1

Pinnington Solar is a 654 MW Solar+Battery project in Texas with status active.

2

Hecate Energy Longhorn Solar LLC is the reported developer.

3

The reported queue phase is IA Executed; proposed COD is 2026-04-30.

4

Latest linked story: “Repsol unveils 637-MW solar farm in Texas” (Renewables Now, 2024-04-12).

Market and operating context

Queue date
2020-12-03
Proposed COD
2026-04-30
IA status
IA Executed
Study phase
IA Executed

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Pinnington Solar — verified asset snapshot

FieldValue
Queue IDERCOT-24INR0010
LocationJack, Texas
TechnologySolar+Battery
DeveloperHecate Energy Longhorn Solar LLC
Market / regionERCOT
Point of interconnection1506 Long Hollow Switch 345kV
Queue date2020-12-03
Proposed COD2026-04-30