Briefing on Pethrus BESS

Entity Briefing
Generated Oct 6, 2026·Dataset freshness not reported
174 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2028-07-25
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Pethrus BESS is a 174 MW Battery project in Texas, currently active.

Pethrus BESS, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-07-25.

Queue ID
ERCOT-26INR0280
Location
Wichita, Texas
Technology
Battery
Developer
Pethrus BESS, LLC
Market / region
ERCOT
Point of interconnection
Tap Wichita Falls Switch (#1464) – North Star (#1467) 138 kV Line

What stands out

1

Pethrus BESS is a 174 MW Battery project in Texas with status active.

2

Pethrus BESS, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2028-07-25.

Market and operating context

Queue date
2023-09-23
Proposed COD
2028-07-25
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Pethrus BESS — verified asset snapshot

FieldValue
Queue IDERCOT-26INR0280
LocationWichita, Texas
TechnologyBattery
DeveloperPethrus BESS, LLC
Market / regionERCOT
Point of interconnectionTap Wichita Falls Switch (#1464) – North Star (#1467) 138 kV Line
Queue date2023-09-23
Proposed COD2028-07-25