Query
Pecan Energy Storage queue pipeline — 1 projects by technology and status
Type
Entity Briefing
Entity
Pecan Prairie North
ISO/RTO
isone
Technology
battery
Generated
2026-10-13T16:47:41.596Z

Briefing on Pecan Prairie North

Entity Briefing
Generated Oct 13, 2026·Dataset freshness not reported
321 MW
Proposed capacity
active
Current status
Solar
Technology
ERCOT
Market / region
2027-05-01
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

Pecan Prairie North is a 321 MW Solar project in Texas, currently active.

CG Leon County II LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2027-05-01.

Queue ID
ERCOT-21INR0428
Location
Leon, Texas
Technology
Solar
Developer
CG Leon County II LLC
Market / region
ERCOT
Point of interconnection
CTT Yellow Wolf, bus # 79007

What stands out

1

Pecan Prairie North is a 321 MW Solar project in Texas with status active.

2

CG Leon County II LLC is the reported developer.

3

The reported queue phase is IA Executed; proposed COD is 2027-05-01.

Market and operating context

Queue date
2019-09-23
Proposed COD
2027-05-01
IA status
IA Executed
Study phase
IA Executed

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Pecan Prairie North — verified asset snapshot

FieldValue
Queue IDERCOT-21INR0428
LocationLeon, Texas
TechnologySolar
DeveloperCG Leon County II LLC
Market / regionERCOT
Point of interconnectionCTT Yellow Wolf, bus # 79007
Queue date2019-09-23
Proposed COD2027-05-01