Briefing/projectactive
Payne Battlecreek is a 85 MW Solar project in Texas, currently active.
Gransolar Texas Ten, LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2027-08-25.
- Queue ID
- ERCOT-24INR0106
- Location
- Hill, Texas
- Technology
- Solar
- Developer
- Gransolar Texas Ten, LLC
- Market / region
- ERCOT
- Point of interconnection
- tap 138kV 213 Haney - 3515 Hubbard
What stands out
1
Payne Battlecreek is a 85 MW Solar project in Texas with status active.
2
Gransolar Texas Ten, LLC is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2027-08-25.
Market and operating context
- Queue date
- 2021-08-12
- Proposed COD
- 2027-08-25
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.