Briefing on Panther Creek 2 Repower

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
8 MW
Proposed capacity
active
Current status
Wind
Technology
ERCOT
Market / region
2026-03-01
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Panther Creek 2 Repower is a 8 MW Wind project in Texas, currently active.

Panther Creek Wind Farm I&II, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2026-03-01.

Queue ID
ERCOT-24INR0582
Location
Glasscock, Texas
Technology
Wind
Developer
Panther Creek Wind Farm I&II, LLC
Market / region
ERCOT
Point of interconnection
Longshore 345kV [Bus# 1058]

What stands out

1

Panther Creek 2 Repower is a 8 MW Wind project in Texas with status active.

2

Panther Creek Wind Farm I&II, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2026-03-01.

Market and operating context

Queue date
2023-06-28
Proposed COD
2026-03-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Panther Creek 2 Repower — verified asset snapshot

FieldValue
Queue IDERCOT-24INR0582
LocationGlasscock, Texas
TechnologyWind
DeveloperPanther Creek Wind Farm I&II, LLC
Market / regionERCOT
Point of interconnectionLongshore 345kV [Bus# 1058]
Queue date2023-06-28
Proposed COD2026-03-01