Query
Paintbrush BESS1
Type
Entity Briefing
Entity
Paintbrush BESS1
State
TN
Technology
battery
Generated
2026-10-19T17:03:07.234Z

Briefing on Paintbrush BESS1

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
201 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2032-10-15
Proposed COD
Briefing/projectactive

Paintbrush BESS1 is a 201 MW Battery project in Texas, currently active.

Renew Development HoldCo LLC is the reported developer. Proposed COD is 2032-10-15.

Queue ID
ERCOT-29INR0222
Location
Coleman, Texas
Technology
Battery
Developer
Renew Development HoldCo LLC
Market / region
ERCOT
Point of interconnection
Tap 345kV 1444 Brown Switch – 60040 Bluff Creek Switch & 1444 Brown Switch – 11406 Central Bluff Switch

What stands out

1

Paintbrush BESS1 is a 201 MW Battery project in Texas with status active.

2

Renew Development HoldCo LLC is the reported developer.

3

proposed COD is 2032-10-15.

Market and operating context

Queue date
2026-01-13
Proposed COD
2032-10-15

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Paintbrush BESS1 — verified asset snapshot

FieldValue
Queue IDERCOT-29INR0222
LocationColeman, Texas
TechnologyBattery
DeveloperRenew Development HoldCo LLC
Market / regionERCOT
Point of interconnectionTap 345kV 1444 Brown Switch – 60040 Bluff Creek Switch & 1444 Brown Switch – 11406 Central Bluff Switch
Queue date2026-01-13
Proposed COD2032-10-15