Query
Padua Grid BESS Unit 3
Type
Entity Briefing
Entity
Padua Grid BESS Unit 3
ISO/RTO
ercot
Technology
battery
Generated
2026-10-17T17:34:18.638Z

Briefing on Padua Grid BESS Unit 3

Entity Briefing
Generated Oct 17, 2026·Dataset freshness not reported
201 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2026-05-15
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

Padua Grid BESS Unit 3 is a 201 MW Battery project in Texas, currently active.

Padua Grid 3, LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2026-05-15.

Queue ID
ERCOT-28INR0024
Location
Bexar, Texas
Technology
Battery
Developer
Padua Grid 3, LLC
Market / region
ERCOT
Point of interconnection
Tap #5395 O.W Sommer 138kV

What stands out

1

Padua Grid BESS Unit 3 is a 201 MW Battery project in Texas with status active.

2

Padua Grid 3, LLC is the reported developer.

3

The reported queue phase is IA Executed; proposed COD is 2026-05-15.

Market and operating context

Queue date
2024-03-22
Proposed COD
2026-05-15
IA status
IA Executed
Study phase
IA Executed

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Padua Grid BESS Unit 3 — verified asset snapshot

FieldValue
Queue IDERCOT-28INR0024
LocationBexar, Texas
TechnologyBattery
DeveloperPadua Grid 3, LLC
Market / regionERCOT
Point of interconnectionTap #5395 O.W Sommer 138kV
Queue date2024-03-22
Proposed COD2026-05-15