Briefing on Orchard Ray BESS

Entity Briefing
Generated Oct 20, 2026·Dataset freshness not reported
52 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2027-05-01
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Orchard Ray BESS is a 52 MW Battery project in Texas, currently active.

Pettus BESS is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-05-01.

Queue ID
ERCOT-25INR0394
Location
Bee, Texas
Technology
Battery
Developer
Pettus BESS
Market / region
ERCOT
Point of interconnection
8590 Tuleta 138kV

What stands out

1

Orchard Ray BESS is a 52 MW Battery project in Texas with status active.

2

Pettus BESS is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2027-05-01.

Market and operating context

Queue date
2023-06-07
Proposed COD
2027-05-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Orchard Ray BESS — verified asset snapshot

FieldValue
Queue IDERCOT-25INR0394
LocationBee, Texas
TechnologyBattery
DeveloperPettus BESS
Market / regionERCOT
Point of interconnection8590 Tuleta 138kV
Queue date2023-06-07
Proposed COD2027-05-01