Query
Obbligato BESS
Type
Entity Briefing
Entity
Obbligato BESS
State
TN
Technology
battery
Generated
2026-10-06T13:48:35.963Z

Briefing on Obbligato BESS

Entity Briefing
Generated Oct 6, 2026·Dataset freshness not reported
201 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2029-02-28
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Obbligato BESS is a 201 MW Battery project in Texas, currently active.

Obbligato BESS, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2029-02-28.

Queue ID
ERCOT-27INR0494
Location
Milam, Texas
Technology
Battery
Developer
Obbligato BESS, LLC
Market / region
ERCOT
Point of interconnection
Tap 138kV 120# TALBRTRIDG – 3683# MINERVA1_8

What stands out

1

Obbligato BESS is a 201 MW Battery project in Texas with status active.

2

Obbligato BESS, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2029-02-28.

Market and operating context

Queue date
2025-06-19
Proposed COD
2029-02-28
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Obbligato BESS — verified asset snapshot

FieldValue
Queue IDERCOT-27INR0494
LocationMilam, Texas
TechnologyBattery
DeveloperObbligato BESS, LLC
Market / regionERCOT
Point of interconnectionTap 138kV 120# TALBRTRIDG – 3683# MINERVA1_8
Queue date2025-06-19
Proposed COD2029-02-28