Briefing on Oak Belt Solar

Entity Briefing
Generated Oct 6, 2026·Dataset freshness not reported
181 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
ERCOT
Market / region
2029-10-15
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Oak Belt Solar is a 181 MW Solar+Battery project in Texas, currently active.

Oak Belt Solar, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2029-10-15.

Queue ID
ERCOT-29INR0243
Location
Victoria, Texas
Technology
Solar+Battery
Developer
Oak Belt Solar, LLC
Market / region
ERCOT
Point of interconnection
Tap 138 kV (Bus #5506) FURHMANSB8 -(Bus #‚Äé5584) VANDERBLTSW8

What stands out

1

Oak Belt Solar is a 181 MW Solar+Battery project in Texas with status active.

2

Oak Belt Solar, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2029-10-15.

Market and operating context

Queue date
2025-12-23
Proposed COD
2029-10-15
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Oak Belt Solar — verified asset snapshot

FieldValue
Queue IDERCOT-29INR0243
LocationVictoria, Texas
TechnologySolar+Battery
DeveloperOak Belt Solar, LLC
Market / regionERCOT
Point of interconnectionTap 138 kV (Bus #5506) FURHMANSB8 -(Bus #‚Äé5584) VANDERBLTSW8
Queue date2025-12-23