Query
Northdraw Wind
Type
Entity Briefing
Entity
Northdraw Wind
Generated
2026-10-19T18:22:08.120Z

Briefing on Northdraw Wind

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
150 MW
Proposed capacity
suspended
Current status
Wind
Technology
ERCOT
Market / region
2020-08-01
Proposed COD
IA Pending
Queue phase
Briefing/projectsuspended

Northdraw Wind is a 150 MW Wind project in Texas, currently suspended.

National Renewable Solutions is the reported developer. The reported queue phase is IA Pending. Proposed COD is 2020-08-01.

Queue ID
ERCOT-13INR0025
Location
Randall, Texas
Technology
Wind
Developer
National Renewable Solutions
Market / region
ERCOT
Point of interconnection
79504 AJ Swope 345kV

What stands out

1

Northdraw Wind is a 150 MW Wind project in Texas with status suspended.

2

National Renewable Solutions is the reported developer.

3

The reported queue phase is IA Pending; proposed COD is 2020-08-01.

Market and operating context

Queue date
2010-06-14
Proposed COD
2020-08-01
IA status
IA Pending
Study phase
IA Pending

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Northdraw Wind — verified asset snapshot

FieldValue
Queue IDERCOT-13INR0025
LocationRandall, Texas
TechnologyWind
DeveloperNational Renewable Solutions
Market / regionERCOT
Point of interconnection79504 AJ Swope 345kV
Queue date2010-06-14
Proposed COD2020-08-01