Briefing/projectactive
Nickel Spruce Solar is a 150 MW Solar project in Texas, currently active.
Nickel Spruce Solar LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-12-15.
- Queue ID
- ERCOT-25INR0342
- Location
- Leon, Texas
- Technology
- Solar
- Developer
- Nickel Spruce Solar LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap 138kV 6735 Pleasant Springs Switching Station - 6736 Middl
What stands out
1
Nickel Spruce Solar is a 150 MW Solar project in Texas with status active.
2
Nickel Spruce Solar LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2027-12-15.
Market and operating context
- Queue date
- 2023-01-30
- Proposed COD
- 2027-12-15
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.