Briefing on New Road Storage

Entity Briefing
Generated Oct 11, 2026·Dataset freshness not reported
120 MW
Proposed capacity
active
Current status
Battery
Technology
PJM
Market / region
2027-09-27
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

New Road Storage is a 120 MW Battery project in Virginia, currently active.

The reported queue phase is IA Executed. Proposed COD is 2027-09-27.

Queue ID
PJM-AE2-019
Location
Loudoun, Virginia
Technology
Battery
Market / region
PJM
Point of interconnection
New Road 230 kV

What stands out

1

New Road Storage is a 120 MW Battery project in Virginia with status active.

2

The reported queue phase is IA Executed; proposed COD is 2027-09-27.

3

Latest linked story: “Virginia gas plant moves ahead despite community objections | Energy” (Bay Journal, 2026-01-07).

Market and operating context

Queue date
2018-12-12
Proposed COD
2027-09-27
IA status
IA Executed
Study phase
IA Executed
Service type
NRIS

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

New Road Storage — verified asset snapshot

FieldValue
Queue IDPJM-AE2-019
LocationLoudoun, Virginia
TechnologyBattery
Market / regionPJM
Point of interconnectionNew Road 230 kV
Queue date2018-12-12
Proposed COD2027-09-27
IA statusIA Executed