Briefing/projectactive
MOUNT LAGUNA WIND 2 is a 400 MW Wind project in California, currently active.
The reported queue phase is C10. Proposed COD is 2031-02-05.
- Queue ID
- CAISO-1429
- Location
- San Diego, California
- Technology
- Wind
- Market / region
- CAISO
- Point of interconnection
- Suncrest - Ocotillo 500 kV Line
What stands out
1
MOUNT LAGUNA WIND 2 is a 400 MW Wind project in California with status active.
2
The reported queue phase is C10; proposed COD is 2031-02-05.
Market and operating context
- Queue date
- 2017-05-01
- Proposed COD
- 2031-02-05
- IA status
- IA Executed
- Study phase
- C10
- Service type
- ERIS
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.