Morning Glory Solar is a 122 MW Solar project in Texas, currently active.
Armadillo Solar, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2026-03-31.
- Queue ID
- ERCOT-23INR0224
- Location
- Tom Green, Texas
- Technology
- Solar
- Developer
- Armadillo Solar, LLC
- Market / region
- ERCOT
- Point of interconnection
- tap 345kV 7077 Amos Creek - 76009 Twin Buttes
What stands out
1
Morning Glory Solar is a 122 MW Solar project in Texas with status active.
2
Armadillo Solar, LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2026-03-31.
Market and operating context
- Queue date
- 2021-06-16
- Proposed COD
- 2026-03-31
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.