- Query
- Montgomery L&D Hydroelectric Project
- Type
- Entity Briefing
- Entity
- Montgomery L&D Hydroelectric Project
- Technology
- hydro
- Generated
- 2026-05-01T10:07:42.118Z
Briefing on Montgomery L&D Hydroelectric Project
Entity BriefingGenerated Jul 1, 2026·Data as of Jul 1
3
Generators
20 MW
Capacity
N/A
Capacity Factor
0
Queue Projects
The Montgomery L&D Hydroelectric Project is a 20 MW planned conventional hydroelectric facility in Pennsylvania, developed by Rye Development, with a CapEx of $1415/kW.
Overview
- Project Name: Montgomery L&D Hydroelectric Project
- Status: Planned
- Technology Focus: Conventional Hydroelectric
- Location: Pennsylvania
- Operator: Rye Development
- Owner: Rye Development
Fleet Details
- Capacity: 20 MW
- Number of Generators: 3
- Grid Interconnections: PJM Interconnection (ISO and BA), RFC (NERC)
Financial Profile
- Capital Expenditure (CapEx): $1415/kW (Source: eia_agg_cost)
Context and Proximity
- Similar Hydroelectric Plants: Emsworth L&D Hydroelectric Project, Tunnel, C W Tippy
- Nearby Industrial/Energy Facilities: Shell Chemical Appalachia LLC, Beaver Valley, Beaver Solar LLC
The Montgomery L&D Hydroelectric Project represents a planned conventional hydroelectric development by Rye Development in Pennsylvania, characterized by a competitive capital expenditure. Its strategic location within the PJM Interconnection and proximity to other energy facilities underscores its potential role in the regional power landscape.